Task in hand: to deduce a discharge stack and pipes of water-supply to the second storey of suburban house.
Progress of work: Installation of discharge stack and pipes of water-supply were conducted to earlier mounted taps from existing systems of water-supply and water removals. At water-supply of the second storey it is necessary properly to calculate and to choose pumping point or pump, for which purpose it is necessary to know the amount of water draw-off points and height of water. In this instance it was performed earlier at development of water-supply system of the house:
Laying of discharge stack and water-supply pipes it was decided to equip in the angle of washroom of ground floor up to exit to the second. For pass through overlapping the apertures of the appropriate diameters were performed:
At installation of the water-supply system we use only polypropylene pipes, as we consider this kind of pipes most reliable and not whimsical in service in connection with solidity of ready design. At installation of polypropylene pipes to hot and cold water it is necessary to take into account that for the pipeline of hot water it is necessary to choose special reinforced pipes, as polypropylene at heating plasticize that can cause a undesired deformation of the pipeline. On the photo below already mounted pipelines of hot and cold water-supply are presented. The plumbing connections were chosen in this instance from residues of Customer but it by no means does not affect structural solidity, and standpipe subsequently will be closed by decorative covering. Naturally that at installation in visible places for best exterrier it is necessary to apply watersupplying pipes and plumbing connections of one colour scale.
After installation of water-supply pipes was installed discharge stack with fastening of its to the wall with the aid of special hose clamps:
When works on installation of discharge stack and water-supply pipes were completed on ground floor, for connection bathroom fixtures and installation of piping connections on the second storey were mounted connector bends:
In more detail with progress of work it is possible become acquainted in our photogallery. Total time of installation of discharge stack and pipes of hot and cold water-supply in suburban house accounted for 1 day.
Не так давно мы писали о том, что в рамках нашей компании было решено открыть еще одно направление работ -…
Рассмотрим поподробнее еще один проект дома от нашей компании (мы также писали о нем ранее). Проект называется "Шерлок", выполнен в…
Рассмотрим подробнее еще один наш проект дома, выполненный в стиле "Барнхаус". Название модного нынче стиля, происходит от немецкого слова "Barnhouse",…
Сегодня рассмотрим один из проектов разработанных нашей компанией, уже построенный и эксплуатируемый порядка 13 лет. Итак, пройдем по основным техническим…
Холодильная камера представлена стационарным оборудованием, которое используется на крупных производствах, в местах общественного питания, супермаркетах, складах и других коммерческих заведениях,…
Для начала давайте разберемся, какие типы проводок можно вообще делать в бревенчатом доме. По большому счету типа два - открытая…